Question 16
Hard
A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 4/7 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A
75 men
B
81 men
C
90 men
D
96 men
Correct Answer:
B
Explanation:
Remaining days = 46 - 33 = 13 days. Remaining work = 3/7. (117 * 33 * 8) / (4/7) = (M2 * 13 * 9) / (3/7) => (117 * 33 * 8) / 4 = (M2 * 13 * 9) / 3 => 7722 = 39 * M2 => M2 = 198 men. Additional men needed = 198 - 117 = 81 men.