Question 1
Hard
2 men and 4 women can complete a job in 5 days. Also same job can be completed by 3 men and 8 women in 3 days. In how many days, twice the job can be completed by 3 men and 3 women?
A
8 days
B
10 days
C
12 days
D
9 days
Correct Answer: A
Explanation:
Equate the total work, with M and W as the daily work of one man and one woman: 5(2M + 4W) = 3(3M + 8W).
10M + 20W = 9M + 24W gives M = 4W, so one man does the work of 4 women.
The job is 5 × (2 × 4 + 4) = 60 woman-days, so twice the job is 120 woman-days. 3 men + 3 women = 3 × 4 + 3 = 15 women, so days = 120 ÷ 15 = 8.