Chain Rule Practice Questions

5 questions per page • Detailed step-by-step solutions

Advertisement
Question 1
Hard
2 men and 4 women can complete a job in 5 days. Also same job can be completed by 3 men and 8 women in 3 days. In how many days, twice the job can be completed by 3 men and 3 women?
A 8 days
B 10 days
C 12 days
D 9 days
Correct Answer: A

Explanation:

Equate the total work, with M and W as the daily work of one man and one woman: 5(2M + 4W) = 3(3M + 8W).
10M + 20W = 9M + 24W gives M = 4W, so one man does the work of 4 women.
The job is 5 × (2 × 4 + 4) = 60 woman-days, so twice the job is 120 woman-days. 3 men + 3 women = 3 × 4 + 3 = 15 women, so days = 120 ÷ 15 = 8.
Question 2
Medium
4 mat-weavers can weave 4 mats in 4 days. At the same rate, how many mats would be woven by 8 mat-weavers in 8 days?
A 16 mats
B 8 mats
C 32 mats
D 12 mats
Correct Answer: A

Explanation:

Mats woven depend on both the number of weavers and the days (output = weavers × days × rate).
One weaver in one day makes \(\dfrac{4}{4\times 4}=\dfrac{1}{4}\) of a mat.
8 weavers in 8 days make \(8\times 8\times\dfrac{1}{4}=16\) mats.
Question 3
Easy
If 5 workers can collect 60 kg wheat in 3 days, how many kilograms of wheat will 8 workers collect in 5 days?
A 140 kg
B 160 kg
C 150 kg
D 180 kg
Correct Answer: B

Explanation:

Wheat per worker per day = \(\dfrac{60}{5\times 3}=4\) kg.
8 workers in 5 days give 8 × 5 = 40 worker-days.
Wheat collected = 40 × 4 = 160 kg.
Question 4
Medium
10 people complete \(\dfrac{2}{5}\)th of work in 8 days working 5 hours each day. How many additional men are needed to complete the work in a total of 14 days working same number of hours each day as earlier?
A 25 men
B 10 men
C 20 men
D 15 men
Correct Answer: B

Explanation:

Man-hours for \(\dfrac{2}{5}\) of the work = 10 × 8 × 5 = 400, so the remaining \(\dfrac{3}{5}\) needs \(400\times\dfrac{3}{2}=600\) man-hours.
Days left = 14 − 8 = 6 at 5 hours a day, so men needed = \(\dfrac{600}{6\times 5}=20\).
Additional men = 20 − 10 = 10.
Question 5
Hard
20 carpets are to be woven by 40 women in 50 days working 8 hours per day. After 20 days, order of 6 more carpets came. To complete the total work on time, how many more hours per day they will have to work?
A 5 hours
B 2 hours
C 3 hours
D 4 hours
Correct Answer: D

Explanation:

One carpet needs \(\dfrac{40\times 50\times 8}{20}=800\) woman-hours.
In 20 days they weave \(\dfrac{40\times 20\times 8}{800}=8\) carpets, so carpets left = 20 + 6 − 8 = 18.
18 carpets need 18 × 800 = 14,400 woman-hours in the remaining 50 − 20 = 30 days, so hours a day = \(\dfrac{14{,}400}{40\times 30}=12\) and the extra hours are 12 − 8 = 4.