Question 6
Easy
If 4 people can do a piece of work in 16 days, working 5 hours each day, in how many days will the same work be completed by 20 people working 4 hours each day?
A
3.5 days
B
4.5 days
C
5 days
D
4 days
Correct Answer: D
Explanation:
The work is fixed, so persons × days × hours per day is constant.
4 × 16 × 5 = 20 × D × 4, i.e. 320 = 80D.
D = 320 ÷ 80 = 4 days.
4 × 16 × 5 = 20 × D × 4, i.e. 320 = 80D.
D = 320 ÷ 80 = 4 days.