Question 21
Easy
If 28 men complete 7/8 of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is = ?
A
2
B
6
C
4
D
8
Correct Answer:
C
Explanation:
28 men do 7/8 in a week → 1/8 needs 28/7 = 4 men.