Question 16
Medium
If 5 men and 3 boys can reap 23 hectares in 4 days and if 3 men and 2 boys can reap 7 hectares in 2 days, then how many boys must assist 7 men in order that they may reap 45 hectares in 6 days?
A
1 boy
B
3 boys
C
4 boys
D
2 boys
Correct Answer:
D
Explanation: