Question 11
Easy
10 men can finish painting a wall in 8 days. How many more men will be needed if the painting work is to be finished in 4 days?
A
5
B
20
C
8
D
10
Correct Answer:
D
Explanation:
10 × 8 = 80 man-days. In 4 days: 80/4 = 20 men → 10 more men needed.