Question 1
Medium
A contract is to be completed in 56 days and 104 men were set to work, each working 8 hours a day. After 30 days, 2/5 of the work is finished. How many additional men may be employed so that work may be completed on time?
A
80
B
56
C
104
D
76
Correct Answer:
D
Explanation:
104 men × 30 days did 2/5 of the work. Remaining 3/5 in 26 days: M = 104 × 30 × (3/5)/(2/5)/26 = 104 × 30 × 1.5/26 = 180 men. Additional men = 180 − 104 = 76.