Aptitude - Time and Work

6.

Ram and Shyam together can finish a job in 8 days. Ram can do the same job on his own in 12 days. How long will Shyam take to do the job by himself ?

Answer

Answer :

Option C

Explanation :


(Ram + Shyam)'s 1 day's work = 18
Ram's 1 day's work = 112
Shyam's 1 day's work = 18112 = 124
Shyam alone can finish the work in 24 days.
7.

A certain number of men complete a piece of work in 60 days. If tehre were 8 men more, the work could be finished in 10 days less. How many men were originally there ?

Answer

Answer :

Option B

Explanation :


Let there be x men originally.
x men finish the work in 60 days and (x + 8) finish it in 50 days.
x men finish the job in 60 days
1 man can finish it in 60x days
(x + 8) men finish the job in 50 days
1 man can finish it in 50(x + 8) days
60x = 50(x + 8) 10x = 400 x = 40
Hence, there were 40 men originally.
8.

A works twice as fast as B. If both of them can together finish a piece of work in 12 days, then B alone can do it in

Answer

Answer :

Option C

Explanation :


Let B's 1 day's work = x. Then, A's 1 day's work = 2x
x + 2x = 112 3x = 112 x = 136
B's 1 day's work = 136
Hence, B can finish the work in 36 days.
9.

A alone can finish a work in 10 days which B alone can finish in 15 days. If they work together and finish it, then out of total wages of Rs. 3000, A will get :

Answer

Answer :

Option C

Explanation :


A's 1 day's work = 110
B's 1 day's work = 115
Ratio of wages of A and B = 110 : 115 = 3 : 2
A's share = Rs. 3000 x 35 = Rs. 1800
10.

A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in :

Answer

Answer :

Option B

Explanation :


B's 9 day's work = 112 x 9 = 34
Remaining Work = 1 − 34 = 14
120 work is finished by A in 1 day
14 work is finished by A in 20 x 14 days = 5 days